Risk Analysis of Time Delays in The Diara Cileungsi Hotel Construction Project Bogor Regency

Dwi Cahya Kusuma

Abstract


The Diara Hotel construction project, which is located in Cileungsi, Bogor Regency, with a building area of approximately 600 m2 and a building height of 24.8 m, has been delayed due to several factors. This study aims to identify risk variables and the highly variable faced by contractors in the risk of time delays in the construction project of Hotel Diara Cileungsi, Bogor Regency. The analysis in this study uses a quantitative descriptive method, which is carried out by surveys, interviews, and distributing questionnaires to respondents. Analysis using software in processing data. The results of the study indicate that there are 34 variables that become risk variables and 7 risk variables with the high ranking risk.

Keywords


Risk Analysis, Diara Cileungsi Hotel, Bogor Regency, Time Delay, The High-Risk Variable

Full Text:

PDF

References


I. W. Y. ASTAWA, N. K. T. TASTRAWATI, and L. P. I. HARINI, “WAKTU PENYELESAIAN PROYEK KONSTRUKSI MENGGUNAKAN PRECEDENCE DIAGRAM METHOD DAN LINE OF BALANCE,†E-Jurnal Mat., vol. 9, no. 3, 2020, doi: 10.24843/mtk.2020.v09.i03.p298.

I. G. K. Sudipta, “STUDI MANAJEMEN PROYEK TERHADAP SUMBER DAYA PADA PELAKSANAAN PROYEK KONSTRUKSI,†J. Ilm. Tek. Sipil, vol. 17, no. 1, 2013.

R. Widyo Kisworo and F. Sri Handayani, “Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off Dengan Penambahan Jam Kerja Lembur Dan Jumlah Alat,†e-Jurnal Matriks Tek. Sipil, no. September 2017, 2017.

R. Howes, “Improving the performance of Earned Value Analysis as a construction project management tool,†Eng. Constr. Archit. Manag., vol. 7, no. 4, 2000, doi: 10.1046/j.1365-232x.2000.00171.x.

Y. (朱艳) Zhu, “Maoming Ethylene Company brain drain and salary management,†2008.

S. P. Rahayu and M. ikhsan Setiawan, “Analysis Of Comparison Of Cost And Time Implementation Of Road Projects Using Methods Time Cost Trade Off,†J. World Conf., vol. 2, no. 1, 2019, doi: 10.29138/prd.v2i1.132.

F. Susilowati and W. M. Kurniaji, “Effective Performance Evaluation to Estimate Cost and Time Using Earned Value,†in IOP Conference Series: Materials Science and Engineering, 2020, vol. 771, no. 1, doi: 10.1088/1757-899X/771/1/012055.

Y. C. Wulan, Y. Yasmi, C. Purba, and E. Wollenberg, Analisa Konflik Sektor Kehutanan di Indonesia 1997 - 2003. Bogor, Indonesia: Center for International Forestry Research, 2004.

Y. Indriani, M. Amir, and I. Mirza, “KEBIASAAN MAKAN YANG BERHUBUNGAN DENGAN KESEHATAN REPRODUKSI REMAJA PUTRI DI KABUPATEN BOGOR,†J. Gizi dan Pangan, 2009, doi: 10.25182/jgp.2009.4.3.132-139.

D. Armbruster, “Keselamatan dan Kesehatan Kerja di Tempat Kerja,†Clin. Lab. Med., 2013, doi: 10.1016/j.cll.2012.10.002.

S. G. Winter, “Developing evolutionary theory for economics and management,†Gt. Minds Manag., 2005.

M. A. Apriliyani, “Analisa Keterlambatan Berbasis Manajemen Risiko Pada Proyek Warehouse Lazada Tahap 2,†Rekayasa Sipil, vol. 8, no. 2, 2020, doi: 10.22441//jrs.2019.v08.i2.02.

J. Wang, Q. Zhang, S. Yoon, and Y. Yu, “Reliability and availability analysis of a hybrid cooling system with water-side economizer in data center,†Build. Environ., vol. 148, pp. 405–416, 2019, doi: https://doi.org/10.1016/j.buildenv.2018.11.021.

Y. Z. Wang, X. L. Chang, and X. P. Wang, “Risk analysis of overlength bored piles construction on complicated geological conditions,†Yantu Lixue/Rock Soil Mech., 2006.

H. M. Kholik and D. A. Krishna, “ANALISIS TINGKAT KEBISINGAN PERALATAN PRODUKSI TERHADAP KINERJA KARYAWAN,†J. Tek. Ind., 2012, doi: 10.22219/jtiumm.vol13.no2.194-200.

E. D. De Leeuw, “To Mix or Not to Mix Data Collection Modes in Surveys,†J. Off. Stat., 2005.

M. Crowell, S. P. Leatherman, and M. K. Buckley, “Shoreline Change Rate Analysis: Long Term Versus Short Term Data,†Shore and Beach, 1993.

A. Arsyad, M. B. Jaksa, G. A. Fenton, and W. S. Kaggwa, “The effect of limited site investigations on the design of pile foundations,†2009, doi: 10.3233/978-1-60750-031-5-2671.

N. Maelissa, W. Gaspersz, and S. Metekohy, “DAMPAK PANDEMI COVID-19 BAGI PELAKSANAAN PROYEK KONSTRUKSI DI KOTA AMBON,†J. SIMETRIK, vol. 11, no. 1, 2021, doi: 10.31959/js.v11i1.21.

Silvianita, S. T. Dian Puspita Sari, Yeyes Mulyadi, and W. L. Dhanistha, “A comparison of application of the project scheduling using precedence diagram method (PDM), line of balance (LOB), and position weight method (RPWM) to construct circulating close cooling water system,†Int. J. Civ. Eng. Technol., vol. 9, no. 13, 2018.




DOI: https://doi.org/10.52088/ijesty.v1i1.305

Article Metrics

Abstract view : 21 times
PDF - 16 times

Refbacks

  • There are currently no refbacks.


Copyright (c) 2021 Dwi Cahya Kusuma

International Journal of Engineering, Science and Information Technology (IJESTY) eISSN 2775-2674